Construction Updates

Project Details

Building Size: 680,640 SF

Site Size: 220 acres

Building Capacity: 3,500 students

Percent Complete: 10%

Estimated Completion Date: Summer 2028

Architect: Huckabee Architects

Contractor: Stewart Builders

Construction Completion

November 2025

Although the rainy weather has been persistent, construction of the new Spring HS is progressing. Reinforced concrete boxes are currently being prepared for installation as part of the new underground storm drainage system. Meanwhile, work on the swimming pool continues, with plumbing being installed before the steel reinforcement (rebar) is added. In addition, the band parking lot has now reached its final ground level and is ready for framing, rebar placement, and concrete pouring. At the same time, the underground electrical system is progressing across the building site and is nearing completion. Finally, at the front elevation of Spring High School, concrete building slabs have been poured for areas 9 through 3, covering more than 130,000 square feet.

Past Updates

October 2025

In October, crews made steady progress across the site. Work continued on the underground electrical infrastructure in Area 12, along with placement of the large 12'x6' storm structures and ongoing installation of the drainage course beneath the natatorium. The athletic track and softball field are quickly taking shape, while the pool walls are being formed in preparation for next month’s concrete pour. Meanwhile, one of the staff parking lots reached a major milestone with the concrete pour completed toward the end of the month.

Electrical Underground
Staff Parking

September 2025

Crews are making steady progress thanks to the great weather. Work is underway on the building foundation, electrical systems, and plumbing. Teams are also drilling support piers and pouring concrete to install drainage systems that will handle both rainwater and wastewater.

August 2025

At the new Spring High School site, crews advanced through essential early construction phases during summer 2025. The land was cleared and graded, with pavement work beginning across key access areas. These foundational steps are preparing the site for upcoming vertical construction.

Throughout the summer, design and construction teams remained in close collaboration with district leadership, aligning features with long-term enrollment trends, instructional programming, and future campus needs. The project remains on schedule, keeping Spring High School’s transformation moving steadily forward.