Construction Updates
Project Details
Building Size: 680,640 SF
Site Size: 220 acres
Building Capacity: 3,500 students
Percent Complete: 10%
Estimated Completion Date: Summer 2028
Architect: Huckabee Architects
Contractor: Stewart Builders
Construction Completion
January 2026
Site work continues to move forward, with underground plumbing and electrical installations actively underway. Reinforcement for the CMU walls is in place, preparing the structure for the next phase of construction. Additionally, the elevator pit for the auditorium has been successfully poured and properly protected, marking another key milestone in the project’s progress.
Past Updates
December 2025
Construction at the new Spring High School continues to make strong progress, with several key areas moving forward this month. Work on the concrete slab is moving in the right direction. The entire 9th grade wing slab has now been completed, marking an important milestone in the building’s foundation. Preparation of the ground (subgrade) is now complete for the baseball field, softball field, and tennis courts. Work has also begun on underground plumbing for the athletic concession building, laying the groundwork for future construction. The band parking lot has been fully poured since the last update and is now complete, providing improved access and functionality for the campus. The detention pond continues to take shape as earthwork progresses. This feature will help manage stormwater and protect the surrounding area. Construction of the pool is advancing well. The pool floor has been poured, and crews are actively applying shotcrete to form the pool walls. Overall, each completed step brings the Spring High School campus closer to becoming a fully functional and welcoming space for students and the community.
November 2025
Although the rainy weather has been persistent, construction of the new Spring HS is progressing. Reinforced concrete boxes are currently being prepared for installation as part of the new underground storm drainage system. Meanwhile, work on the swimming pool continues, with plumbing being installed before the steel reinforcement (rebar) is added. In addition, the band parking lot has now reached its final ground level and is ready for framing, rebar placement, and concrete pouring. At the same time, the underground electrical system is progressing across the building site and is nearing completion. Finally, at the front elevation of Spring High School, concrete building slabs have been poured for areas 9 through 3, covering more than 130,000 square feet.
October 2025
In October, crews made steady progress across the site. Work continued on the underground electrical infrastructure in Area 12, along with placement of the large 12'x6' storm structures and ongoing installation of the drainage course beneath the natatorium. The athletic track and softball field are quickly taking shape, while the pool walls are being formed in preparation for next month’s concrete pour. Meanwhile, one of the staff parking lots reached a major milestone with the concrete pour completed toward the end of the month.
September 2025
Crews are making steady progress thanks to the great weather. Work is underway on the building foundation, electrical systems, and plumbing. Teams are also drilling support piers and pouring concrete to install drainage systems that will handle both rainwater and wastewater.
August 2025
At the new Spring High School site, crews advanced through essential early construction phases during summer 2025. The land was cleared and graded, with pavement work beginning across key access areas. These foundational steps are preparing the site for upcoming vertical construction.
Throughout the summer, design and construction teams remained in close collaboration with district leadership, aligning features with long-term enrollment trends, instructional programming, and future campus needs. The project remains on schedule, keeping Spring High School’s transformation moving steadily forward.